How it works

A daily water account for each canal reach, checked on the ground and turned into the division's repair list.

Operators and tail-end farmers report what the canal is doing, NaharWatch works out where water is going missing, the Section Officer walks that stretch, and engineers rank what they find in the Department's own repair categories.

01In one minute

Five steps, from a gauge reading to a repair

02What changes

Today, and with NaharWatch

Today
With NaharWatch
Finding where water is lost
A complaint from the tail, then a walk along the canal to find the cause.
The water account points to the reach between two gauges, so the walk is about 1.5 km.
Knowing the tail got water
Estimated in the monthly return.
A farmer at each last outlet replies once a day. Days the tail got water are counted, not estimated.
Spotting a slow failure
Noticed once it is visible on the bank.
Each reach's loss is tracked week by week, and a steady rise is flagged before the bank gives way.
Recording a defect
Notebooks, phone photos and letters, kept by whoever found it.
A photo taken in the app at a chainage, with type and severity, saved on that asset's history.
The M&R priority list
Framed by each division when the budget is communicated.
Ranked through the year in the SOP's five categories, each item with its evidence pack.
Flood damage
Reported separately to IPMS and to DRIMS.
Recorded once on the walk, then pushed to IPMS and prepared for DRIMS.

The "Today" column is drawn from the challenge statement and the Department's 2024 O&M procedure. We'll walk through the real process with a division during discovery.

03The challenge, point by point

What the Department asked for, and where to see it

The challenge asks forWhat NaharWatch does
Identify and geolocate abnormal conditions or suspected defectsThe water account flags the reach losing water. The Section Officer records the defect at a chainage with an in-app photo. Radar after floods adds hints on where to walk.See it
Prioritise maintenance based on condition and riskA ranked M&R list: severity, area served below the defect, water lost and repeat failures, each with its reasons and SOP category.See it
Mobile field capture and central dashboardsAn offline Android app for Section Officers and operators; web screens for AEEs and EEs; WhatsApp, SMS or missed call for tail-end farmers.See it
Retain evidence and status of inspection and corrective actionEach defect keeps its trail: signal, field report, confirmation, work order, before and after photos, closure. Nothing is overwritten.See it
Earlier detection of defects and abnormal water lossesWeek-by-week loss for every reach, compared with its own usual figure, and a daily tail-end reply.See it
Reduced inspection burden and avoidable disruptionWalks go to the stretch that is losing water. Routine walks continue for structures on their usual cycle.See it
Analytics for predictive maintenanceA watchlist of reaches whose loss is rising, and a record of every flag's outcome to train a model once enough seasons exist.See it
Combine modelling or GIS data with ground information; actionable alertsA simple flow model per reach, fed by gauge readings and checked against replies and walks. Every flag becomes a dated task for a named officer.See it
Detailed breakdownWater account and flag rules · Priority score · Workflows · Architecture and security · Discovery
ARules and scores

How a reach's loss is worked out

Each reach runs between two gauges. Flow at a gauge comes from its water level and the structure's rating table, starting from the design discharge tables and checked with a few current-meter readings in the first season.

Loss in reach = Q upstream gauge − known offtakes − Q downstream gauge
Unusual if loss > 3 × the reach's own median of the last 4 weeks, and > 0.1 cumec
SignalRule (starting point)What happens
Unexplained lossAs above, on two readings in a rowWalk task for the Section Officer within 2 days; AEE informed
Creeping lossLoss up three weeks running, still below the flag lineReach goes on the watchlist; walked on the next routine round
Tail-end reply"No water" once, or "low" three days runningWalk task at the outlet and the reach above it
Muddy seepage or bank crackReported on any walkImmediate alert to AEE and EE; the field report is marked urgent
Radar or optical hintGround change beside a bank after a floodSuggested walk only; never a repair without a field check

How the M&R list is ranked

FactorFromWeight (starting point)
Severity, 1 to 5The Section Officer's report, confirmed by the AEE35%
Area served below the defectCommand area of every outlet downstream30%
Water being lostThe water account, where the defect explains a flagged loss20%
Repeat failurePast repairs on the same asset15%

These rules and weights are starting points. We'd agree the real ones with the Department's engineers in the first three weeks, and the EE can always move an item with a written reason. The only AI in the system reads the number off a gauge photo; the operator confirms every reading, and a low-confidence read asks them to type it.

BWorkflows

From a lost cumec to a line on the M&R list

Operators, 7 am
Gauge readings
Photo of the staff gauge at each regulator; loggers send theirs on their own.
NaharWatch
Water account
Loss per reach, against its own usual. Tail replies come in alongside.
Section Officer
Walks the reach
Checks the banks, outlets and structures in that stretch; records what's there.
AEE
Confirms
Checks the photos and location, sets the SOP category and funding route.
EE
M&R list
The item joins the ranked list with its evidence pack and goes to IPMS.

The M&R year, as the 2024 SOP sets it

Start of the M&R year
Proposals invited
The ranked list is already there, with the evidence the estimates need.
By 30 June
Priority list and AA
The approved priority list goes to Government for AA in early July. Contractors are empanelled at the start of the year.
By August
Work orders
Issued from the list; work starts within three days.
By end November
Works complete
After photos from the same spot close each work order.
By 15 December
Financial sanction
The closed works, with before and after photos, go up for FS.

The second flow follows section 15 of the Irrigation Department's SOP for Operation and Maintenance of Irrigation Schemes (2024).

CArchitecture

Small pieces of hardware, one field app, one set of records

Our live platform runs the same roles, approvals, photo capture and notifications engine. NaharWatch adds the water account, the flag rules and the M&R list. It can be hosted on the State Data Centre or a MeitY-empanelled cloud.

People
Gate operators
Tail-end farmers
Section Officers
AEEs and EEs
CE office, O&M
Apps and devices
Android field appoffline, in-app camera, Assamese and English
Web app for engineers
WhatsApp, SMS, missed call
Level loggersultrasonic, solar, GSM; 1–2 per scheme
Core
Gauge photo reader
Water account and flag rules
Defects and work orders
M&R list and evidence packs
Audit logappend-only
Data
PostgreSQL + PostGISreaches, chainages, assets
Level and flow time series
Photo storage
Connects to
IPMSschemes in, damage entries out
Khetiyak Bondhu issues
DRIMSflood damage format
Sentinel-1/2hints after floods

Access by role

Operators see their regulator, Section Officers their section, engineers their sub-division or division. Officers sign in by OTP.

Nothing is overwritten

Every reading, report, confirmation and closure is logged with who, when and which device. A correction makes a new version.

Photos that are hard to fake

Taken only in the app, stamped with location and time, checked for fake locations and duplicates. After photos are matched to the before photo's spot.

Farmers' numbers kept private

Tail-end reporters join with consent and can stop any time. Their numbers are masked in every report (DPDP Act 2023). Canal maps stay with authorised users.

DDiscovery

What we'll settle with the Department in the first three weeks

The design rests on the challenge statement, the Department's 2024 O&M procedure and public information on IPMS. These are the points we'll confirm with a pilot division before building the production system.

  • Which regulators on the pilot schemes have staff gauges and operators, and where the two level loggers should go.
  • Design discharge tables and rating curves for those regulators, and the outlet list with design offtakes.
  • What IPMS holds below scheme level, and how NaharWatch reads from and writes to it.
  • The DRIMS damage-report fields for irrigation assets.
  • Who frames the M&R priority list in a division, and in what format it goes to the CE.
  • Which farmers at the last outlets are willing to reply, and on which channel.